1/22: Convention Center Slab Poured

Happy Friday! Old Man Winter reared his ugly head this week and the weather wasn’t so good, windy and cold. We lost 4 of the 5 days on the roof so not much progress there. Our roof is key to schedule however we anticipated having some bad weather so we are still on track! We poured the Convention Center slab on grade as planned and are still moving forward with our underground plumbing , electrical and refrigeration lines. Our Carpenters missed a couple days on roof parapet work due to weather, but are ahead of the roofers so no harm done. Block layers are continuing in the locker room areas between the two Arenas and the Iron workers finished setting the steel for the Convention Center Canopy. Things are shaping up we just want the weather to continue to cooperate! Have a great weekend everyone!