10/23: Concrete Piers

Happy Friday All! This week again has not treated us well as far as the weather is concerned. Old man winter has reared his ugly head. We had an ok week considering the weather. We poured the last of the concrete piers and only have approximately 10 stoop foundations left to pour. Our precast installation started as planned on Tuesday. The weather affected trucking but we still installed approximately 300 feet of wall. The building
will change a lot in the coming weeks. It’s showtime! We are continuing with masonry bearing walls and will finish them next week. We received our first load of steel yesterday and will start what steel erection we can next week. Our earthwork was hit the hardest this week, not much was done due to the extremely wet conditions. Next week looks better! Have a great weekend everyone!