12/18: Last of Precasts Set

Good afternoon everyone! We had another good week on the job site. Although there were a number of challenges, we prevailed! Wells Concrete set the last of the precast wall panels this morning! This is a giant milestone! Plumbers and Electricians have been working on the underground on both the North and South ends of the building and we will start prepping to pour our first flab on grade next week! The Ironworkers set all the long span joists at the convention center area to keep our metal stud work on the exterior going. The roofers finished roofing the east side of the convention center and started roofing on the North end of the building! Have a great weekend and a wonderful Holiday Season!

Update provided by Superintendent Gary Francisco,
Kraus-Anderson Construction Company