3/1: Thawing Out

Happy Friday All!
Now that the Polar Vortex has left us, we have been thawing things out and picking up the pace once again! Our outside activities are in full force. Roofers had a decent week and were able to install 3 days so far with 2 days lost to the wind. We will be working this Saturday to try and pick up some ground. We are also installing an air barrier on the exterior walls and windows in the precast openings! Inside we continue with metal stud framing, Masonry walls, underground and overhead plumbing, and electrical work, sprinkler rough-in and dirt work in the West Arena. We poured the slab on grande in the North mechanical/ice plant rooms and waterproofed the second-floor mechanical room at the Convention Center. It was a good week! Have a wonderful weekend everyone!

Leave a Reply