3/5: Roofing Finished!

Happy Friday Everyone! We had a great week this week! The weather was awesome! We continued with underground and overhead rough-ins, finished the block walls in the locker room area, continued patching precast walls, put air handlers up in the North Mezzanine, set the big chiller on the North Mechanical room roof, prepped for our Convention Center topping slab and finished the air barrier on the exterior of the building, and finished piping the main lines for the secondary rink. We also hit a giant milestone, and finished the roofing on the last roof at the main Arena! We have a big week scheduled for next week. We will be installing spray foam at the exterior stud walls, Pouring our last topping slab on the second floor and we hope to pour the last of the slab on grade in the Convention Center and much more!