9/18: Footings & Foundation

Happy Friday Everyone! As the weather starts to turn a little colder we are once again reminded that winter is coming! We had a good week this week. There were no weather delays! We continued on with footings and foundation work and site utilities. We had some soil correction issues in the west parking lot but our MECC team worked together diligently to keep the project moving without delay. For those of you who have driven by the site,