10/23: Concrete Piers

Happy Friday All! This week again has not treated us well as far as the weather is concerned. Old man winter has reared his ugly head. We had an ok week considering the weather. We poured the last of the concrete piers and only have approximately 10 stoop foundations left to pour. Our precast installation started as planned on Tuesday. …

10/16: Precast Prep

Happy Friday All, As we begin to make the transition from Fall to winter, the weather has not treated us very well. This week we were rained out on Monday and Wednesday. 2-1/2” of rain total at the site. Even though our week was cut short by Mother Nature we managed to get a lot done by working some long …

10/09: Soil Corrections

Happy Friday Everyone! Our weather this week was great! Our Earthwork crew had to be in quarantine this week however TNT was able to get another crew on site to continue with soil corrections. A massive amount of select granular was brought in and placed this week. The majority of the West lot and roadways around the building have been …

10/02: Footings & Arena

Happy Friday Everyone! We had a little scare last week concerning COVID-19. We followed the proper protocol and didn’t miss a beat on the project. We continued on with concrete footings and walls in area A Arena and laying the concrete block in the Area A Arena for stadia along with a floor plank bearing wall by the elevator. Our …

9/18: Footings & Foundation

Happy Friday Everyone! As the weather starts to turn a little colder we are once again reminded that winter is coming! We had a good week this week. There were no weather delays! We continued on with footings and foundation work and site utilities. We had some soil correction issues in the west parking lot but our MECC team worked …