Happy Friday All! We had an interesting week this week. The weather was better than last week and will be even better next week! We continued on with Earthwork, hauling fill to the site and digging ponds and misc. backfill. Our Masons were not here this week due to COVID Concerns. We have adjusted our activity on-site to accommodate their absence and remain productive. We are continuing with setting pre-cast panels and plank. Our
natural gas and permanent power lines were run into the site and our transformer is supposed to be here next week. Today, 10 semi loads of joist and deck are being delivered. We will start steel erection next week. Although it can never be fast enough for my liking, things are progressing nicely on site. Have a great weekend everyone!